April 2, 2007
Commissioning activities are underway and proceeding well at the UPC Steel Winds project site. Rotors have been installed on all eight wind turbines and two turbines are now delivering power to the grid.
Endeavor construction activities continue, with a significant number of components staged at the site. Turbine rotor installation has now commenced.
At Clipper's Cedar Rapids manufacturing and assembly facility, a total of 14 Liberty® wind turbines were completed in March. Series production through March totaled 32 model 2.5 MW Liberty wind turbines, including the eight produced in 2006.
back
|
|
|